A simple introduction to portal scaffolding sequence.

2018-04-08 22:01:03
News details

Gantry scaffolding, order: basic preparation to put plate, put the base to set two common monolithic door frame, install the crossbars to install scaffolding, on this basis, repeat install door frame and cross bar, scaffold board process.

The scaffold shall be constructed from one end to the other, and the scaffolding shall be carried out after the scaffold is built. Set the direction opposite to the next step.

Step door scaffold erection, should first base in the endpoint insert two common door frame, and then fitted with fixed cross rod, lock the lock plate, and then after the erection of the door frame, each cross, cross rod and locks fitted immediately. The scaffold must be securely attached to the building. The outside should be equipped with scissors support, vertical and vertical should be set continuously.